Contractor:
Hazard Construction. County issued Notice to Proceed (NTP) November 12, 2025.
Project Summary:
- Phase 1: Mobilization and night test strip (15 days allotted for testing; 24-hours to cure before coring). COMPLETE
- Phase 2: 30-day full runway closure for milling and reconstruction (south end full-depth reclamation and cement-treated base; north end milling + overlay without dig outs). Add new shoulder backing on Runway 2 to improve drainage.
- Phases 3/4: 30-day BMP/curing period with temporary striping for reopening; final striping done in a one-day closure after curing.
Funding:
- Federal Aviation Administration (FAA) ~ 95%; County share ~ 5%
-
This was determined grant-eligible per County’s Pavement Management Program (PMP).
-
We received a federal fiscal year 2025 grant for design and FY2025 for construction.
-
The County Board approved the project in 2024.
Frequently Asked Questions:
-
Tenant/hangar access: Airport tenants will retain vehicular access to their hangars and facilities at Fallbrook Airpark via the northern airpark road for the duration of the project.
-
Relocation options: Temporary and free relocation is available at other San Diego County Airports. Note that relocation to Palomar requires badging and wait times.
-
Security: Contractor will provide a guard at the main access when the access gate is in use for construction purposes; county security coverage is 7 days/week. Confirm daily hours, point-of-contact, and continuity during company transition.
-
Taxilane Pavement Repair: DPW Airports will be coordinating Taxilane B repair which will commence the week of January 19. Work shall not last more than 5 days, contingent on weather.
-
Runway profile ("hump"): This particular section of the runway is being rehabbed to a depth of 9” and final runway grades will surveyed per plan and do not include a “hump”.
Contacts:
Relocation:
County of San Diego Airports Associate Real Property Agent Tia McLaurin at Tovonnia.McLaurin@sdcounty.ca.gov. Relocation of your aircraft to Palomar Airport will require badging and wait times.
Airport Director:
Jamie Abbott
Email: Jamie.Abbott@sdcounty.ca.gov
Fallbrook Airpark Operational Staff:
Cell: 760-723-8395
Runway Project Manager:
Cynthia Curtis
Documents & public resources :
-
Bid documents, phasing plans and ACIP are public on the county BuyNet Purchasing and Contracting.
-
Airport Capital Improvement Plan (ACIP) updated annually and listed on website ACIP
Project Milestones:
Phase 1: Test strip
- Materials Test:
- Mobiliization: Sunday Dec 7, 2025
- First Test: Tuesday Dec 9 - Thursday Dec 11, 2025
Phase 2: Runway work (Monday Jan 19 - Friday Feb 20, 2026)
Phase 3: 30-day Stormwater Best Management Practice (BMP) Maintenance
Phase 4: Final striping (30 dyas after end of Phase 2 work)