UST Plan Check FAQs
When is a permit from the HMD needed?
A permit from the HMD is required when an underground hazardous materials storage tank system (UST system) is constructed, repaired, modified, or closed. A UST system includes the tank(s), all piping (vent, vapor, product lines), UDCs, and associated equipment. A permit is required for the following:
- Installation of a new UST system.
- Removal or closure in place of any component of a UST system.
- Modification or repair of any component of a UST system.
- Secondary Containment Testing repairs.
- Installation or replacement of leak detection equipment.
- Installation or modification of a corrosion protection system.
Please contact our UST Plan Check staff if you need more
information or assistance to determine if your project requires a UST
permit.
What steps should I take to obtain a UST Plan Check Permit?
Obtain and complete the appropriate HMD application form(s). You may also request that the forms be emailed to you, please contact USTNotifications.LUEG@sdcounty.ca.gov.
- Obtain other permits, as needed, from the local fire department, Air Pollution Control District (APCD), and local building/planning department, if applicable.
- Obtain and/or include a Board of Equalization (BOE) number.
- Obtain and/or include an Assessors Parcel number.
- Prepare plan drawings (submit the original and two copies).
PLEASE NOTE: Tank removals do not require a permit from the APCD or a BOE number, but do require that you complete a UST Closure Work-Plan (to be completed by the contractor) and a Post Tank Removal Work-Plan if question 4 of the application is marked "yes".
How long will it take to get my permit reviewed?
Provided that all the required documents have been properly
completed and that all applicable fees have been paid, most plans are
reviewed within 7-10 working days. The plan check technician
will notify you by phone when your application package has been
reviewed.
How do I schedule an inspection?
Inspection scheduling must be made 48 hours in advance and is based
on inspector availability.
It is important that you check with
other agencies as needed (i.e. Fire Department) before scheduling an
inspection with DEHQ.
You can call the plan check message line
at 858-505-6785 to schedule an inspection appointment. All inspections
are scheduled in a first come first served basis. Messages will be
recorded in the order they are received. We will do our best to
accommodate your preferred date and time based on inspector
availability. Within 24 hours of your call, you will receive
confirmation of a scheduled inspection date and time. Request for
specified inspection dates and times due to special circumstances will
be handled only on a case by case basis.
Please leave the following information when making an appointment. Failure to do so may delay your request:
- Name
- Contact phone number to return call
- Establishment number
- Plan Check number
- Inspection Type (pressure, final, removal, etc.)
- Preferred inspection date (minimum 48 Hours notice is required)
- Preferred inspection time (9:00 am or 1:00 pm appointments only)
How do I cancel an already scheduled inspection?
To cancel your scheduled inspection you must contact the plan check
technician at (858) 505-6976 at least one hour before the scheduled
inspection, or a fee will be assessed.